Inspection planning
An inspection concept starts with the right question
What needs to be established about a component? Connect requirements, methods and evidence before choosing equipment.
2 min readUpdated: Editorial team: NPB NDT Consulting
Define the task before selecting equipment
An inspection concept sets out the intended inspection statement and the conditions under which it is valid. Start with component function, material, geometry, manufacturing condition and the discontinuities of interest. An equipment list cannot replace this work. The position in the manufacturing sequence also matters: machining may change which regions are accessible.
NPB NDT Consulting
From inspection task to series production
Consider inspection technology, production and quality together.
- 01
Clarify requirements
Component, quality objective and inspection extent
- 02
Develop the inspection concept
Methods, feasibility and evidence
- 03
Support integration
Handling, system functions and data interfaces
- 04
Coordinate system ramp-up
Procedures, system checks and documentation
- 05
Train the team
Operation, roles and escalation routes
- 06
Support series production
Monitoring, changes and improvements
Technical requirements · Clear interfaces · Traceable implementation
Turn requirements into verifiable steps
Agree the inspection regions, applicable specifications and evaluation basis with the responsible quality team. Include reference checks, invalid inspections and the handling of cases requiring clarification. An indication is not automatically a rejectable defect; evaluation requires the agreed criteria and context.
Prepare implementation together
Production, NDT specialists and the equipment supplier need a shared requirements baseline. A simple link between each requirement, its proposed implementation and the planned evidence helps identify gaps. Give open items an owner and a due date. Assess changes to the component or production sequence for their effect on the concept.
Practical checklist
- Define component condition and inspection stage
- Describe inspection regions and the required statement
- Agree evaluation and clarification routes
- Assign evidence and responsibilities
Planning example
Illustrative planning example, not a customer reference.
Planning example: For a machined forging, consider inspection of the blank separately from any supplementary inspection after machining. Combining the results requires a technical assessment of what each inspection establishes.
Key takeaway
The outcome is a shared technical basis for procurement, inspection and documentation, with explicit limitations.
Technical sources
- DGZfP – NDT methods (external link, opens in a new tab)
- TWI – Non-destructive testing (external link, opens in a new tab)
The articles and method descriptions provide general technical orientation. The organisations listed are technical sources, not customers or partners of NPB NDT Consulting. Sources may be in German or English.
These articles provide technical orientation. The specific inspection task and applicable requirements must be assessed for each project.
Would you like to apply this question to your component or process? Start by describing the task in general terms.
Related articles
Inspection planning
FAT, SAT and ramp-up: plan the evidence early
2 min read
Mechanical engineering
NDT in mechanical engineering: plan inspection early
2 min read
Automation
Which level of automation fits the inspection task?
2 min read